Payback Period (Pt, 静态投资回收期)
The time it takes to pay back the investment, i.e., the number of years required for CIs to be just equal to COs.

t — Year at the end of which the cumulative NCs is positive.
Decision Rule
If Pt ≤ N, the project is economically justified.
If Pt > N, the project is not accepted.
Simple Rate of Return(简单收益率/投资效果系数)
Simple Rate of Return is the inverse of Payback Period

If a project is perpetual or its service life is extremely long with infinite uniform cash flows,
Simple Rate of Return can be used to roughly represent the IRR of a project.

Discounted Payback Period (Pd, 动态投资回收期)
The time value of money is considered.


Decision Rule
If Pd ≤ N, the project is economically justified.
If Pd > N, the project is not accepted.