  • 1 Construction Team
    • 1.1 construction team
    • 1.2 project organization
    • 1.3 civil engineer
    • 1.4 architect
    • 1.5 structural engineer
    • 1.6 service engineer
    • 1.7 quantity surveyor
    • 1.8 building contractor
    • 1.9 technicians
    • 1.10 operatives
    • 1.11 building surveoor
    • 1.12 building inspector
    • 1.13 Conversation of Prequalification
  • 2 Precontract phases
    • 2.1 precontract phases
    • 2.2 breifing phase
    • 2.3 proposal phase
    • 2.4 detail design phase
    • 2.5 contract & tender processes
  • 3 Architectural features
    • 3.1 drawing of house
  • 4 Materials
  • 5 Substructure
detail design phase

detail design 1 

As a basis for obtaining planning permission and building regulation approval, the following will be required: 

location plans and block plans, indicating boundaries with 邮tancesto neighbouring properties, roads and footpaths, the building site/plot and ratio of built area to plot size, etc

orthographic drawings (front, end, plan and sectional eleva­tions) of the construction to be undertaken

elevations indicating foundation depths, roof ridges and other important points of the project

detail drawings of construction methods for building regulation approval

a completed planning application form obtained from the local authority.


detail design 2

In order to go to tender the following will normally be required

complete sets of detailed working drawings for each trade area involved in the project

a pre-qualification notice for the tender process the client wish­es to use

a set of tender forms for the contractor(s) to fill in his/her bid with space for provisos the contractor(s) may wish to make

a set of specifications to include:

1. the project specification

2. the contract specification

3. a works specification - one for each trade area

4. building components specification

a bill of quantities

a tender control plan for each of the trade contracts

a tender time schedule

a performance bond, a guarantee usually signed by the con­tractor's bank indicating support for the contractor in cases of financial difficulty.